Rail To Trail Bulletin No. 10
November 12, 2000
By Paul Beckett
INTRO. NOTE: This is likely to be the last "bulletin" of this construction
season. If you would like these informational bulletins to be resumed
when construction resumes next spring, send an email to that effect to me
at pbeckett@facstaff.wisc.edu.
Thanks!
Since the last bulletin (No. 9) by Kurt Kiefer and me, slightly depressed
in tone, there has been better progress, and while Wisconsin weather will
(of course) have the final say, it looks like the fall's construction
goals will be achieved before the heavy machinery goes into winter
storage.
Our neighborhood has been very fortunate to have an extremely cooperative
relationship with the Path construction supervising engineer, Aaron
Palmer. Aaron has talked with many residents individually, and has been
able to help with a number of concerns. He has been constantly
forthcoming and frank with updates on the construction process, and on
possible problems or delays. Aaron met on November 1 with the DMNA Rail
to Trail committee and provided a very complete update on the Path. And
in lieu of a construction meeting on November 9 Aaron wrote a similarly
illuminating summary. The rest of this bulletin is drawn mainly from
Aaron's reports, with only minor editing and shortening.
-
The contractor has laid base course from the Capitol City trail all the
way up to Glenway. This first layer that went in last Thursday and Friday
was only about 4" thick. The next step is for the surveyors to pound a
stake every 100' over this layer to the desired base course elevation.
This is called "red tops", as opposed to "blue tops" for subgrade
elevation. The next step will be for Wingra, the base course
subcontractor, to bring in more gravel and finish grade the trail to the
appropriate elevations and grade. This has occurred from the Capital City
trail to the Beltline and is about 90% complete from Midvale to Odana.
-
Recycled asphalt has been used for the base course on the first lift that
went in. Subsequently, 3/4" crushed limestone (what is typically thought
of as gravel) has been laid on top as the finish grading. This is easily
identifiable by the difference in color between the two.
-
The next step for south of the Beltline, from the junction with the
Capital City Bike Trail to the Beltline bridge, is paving. This time of
year everyone is scrambling to get things paved and thus the subcontractor
for paving, Payne and Dolan, is extremely busy. Henshue Company says that
Payne and Dolan will begin laying the asphalt paving as soon as they free
up a crew.
-
The Midvale crossing, which involved large-scale new drainage works, has
been very time consuming. But work on Midvale is nearing completion. One
lane has now been paved. The median now must be cleaned and landscaped,
and the sidewalks must be constructed. At a minimum, traffic will be
restored to normal by close of business, Friday the 17th of November.
-
Closer to home, Odana is in about the same status as Midvale. Remington
Electric must place electrical conduit across the road. The outside curbs
and gutters and sidewalks must be constructed. We will have to let the
concrete work sit about a week before we can mill (grind) off some of the
asphalt and lay new asphalt back on it to match the curb and gutter.
-
The Henshue Company (the main contractor) has started lowering the water
main at the Virginia Terrace to Sheldon-Fox crossing. They need one good
day of weather to finish. Since construction has begun, it has become
apparent that a new addition to the drainage plan will be required in the
area between the Virginia Terrace to Sheldon-Fox crossing and the
underpass at Hillington. Neighbors there have noted increased washing of
mud. A new pipe and inlet will be placed and connected to the existing
storm sewer at Fox Avenue near the underpass. It will basically parallel
the path of the gas main that was installed last summer. Tony Fernandez
of City Engineering has scheduled a meeting with the neighbors in this
area to explain the plan. Henshue will put this in as soon as they
complete the water main work.
-
Henshue still plans on getting a layer of base course down the entire path
this year. That may not happen until things freeze up. The base course
can be laid on frozen ground if necessary. Also, the paving south of the
Beltline will be done even if the trail freezes first.
-
Henshue has received the materials for reconstruction of the underpass
bridge between Hillington Green and Fox Avenue. Construction is expected
to begin soon. Once it starts, it will be necessary to close the
underpass for at least a month. WE ASK NEIGHBORS' COOPERATION IN
RESPECTING THIS CLOSURE, WHICH IS NECESSARY TO GET THE JOB DONE.
-
It is expected that the several retaining walls required WILL be done this
fall, but the schedule is uncertain. Aaron is checking with the
subcontractor for these walls.
-
Remington Electric is laying the electrical conduit along the path. As
residents will recall, nighttime lighting will NOT be provided along our
neighborhood, except as required at street intersections. However, it was
agreed that conduit should be laid for possible future use.
Aaron Palmer may be contacted by email at Graef, Anhalt, Schloemer &
Associates at aaron.palmer@gasai.com .
Neighbors who have problems or questions can also phone him at the Odana
Street field office at 218 1517.
As always, neighbors who wish to discuss special problems or questions can
email (preferred) or phone Paul Beckett (pbeckett@facstaff.wisc.edu )
or Kurt Kiefer ( kkiefer@madison.k12.wi.us ).
http://www.dmna.org/bikepath/bulletin10.shtml
Last Modified: 03-Feb-08 05:53 PM
_
Contact Us: webmaster@dmna.org or ekelana (at) gmail.com
Copyright © 2000 - 2003, Dudgeon-Monroe Neighborhood Association
Madison, Wisconsin